Recently, Paul Bateman at AVT Australia was asked to install insertion valves in the tight quarters under the small outdoor stairwell of the
Melborne Arts Center (below).

MelbourneArtsCenter

The task seemed simple enough, install two, 8” (200mm) EZ™ Valves on 80º C (176º F) hot water lines and two, 10” EZ™ Valves on 6º C (42.8º F) chilled water lines. However, two of these pipes ran 4 inches from the ceiling, making a standard "rightside up" installation impossible.

upside down 3low

 

 

 

 


So we improvised.

upside down 1low    upside down 2low

We can now claim to be the experts at upside down EZ™ Valve installations.

rightside up 1low    rightside up 2low

We also developed some special tricks to remove swarf on the first 10” (250mm) and some engineering changes to the location of the chip flushes. Both worked perfectly.

acrobat
Click Image to Download Complete PDF Version of The Melbourne Arts Center Story